Chiswick War Memorial Homes

Project Description

Chiswick War Memorial Homes was a two phase development consisting of the design and construction of 28no flats and a community centre, plus the refurbishment of 8no houses with extensive external works. The dwellings provide accommodation for ex-service personnel with a range of disabilities.

The scheme is constructed in timber frame, with 10% of the energy requirement provided by renewable energy through the installation of solar panels. Level 3 of the Code for Sustainable Homes was achieved by obtaining a 25% reduction in carbon emissions, using water saving devices, high levels of insulation, rainwater attenuation, using
materials with low u-values and achieving high levels of air tightness.

The first phase of the development completed in June 2009 with the second phase completed in July 2010.

Project Details

  • ADDRESSBurlington Lane, Chiswick, London, W4 3EU
  • CLIENTSir Oswald Stoll Foundation
  • ARCHITECTLiving Architects
  • ENGINEERSEllis & Moore Consulting Engineers
  • CLIENT REPRESENTATIVEMaddlin + Maddison
  • M&E CONSULTANTSAJD Design Partnership
  • CONTRACT SUM£5.6m
  • COMPLETION DATEJuly 2010